Changes between Version 2 and Version 3 of projects/2008_colo_move


Ignore:
Timestamp:
Jul 1, 2008, 4:20:59 PM (17 years ago)
Author:
Jamie McClelland
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • projects/2008_colo_move

    v2 v3  
    1111We should start with a Lowdown as soon as possible that describes how we went through this process and how the move gives us twice the bandwidth and electricity. I also think it's important to mention Micah's role in particular and our plans for working more closely with Riseup.
    1212
    13 === Service Advisory ==
     13=== Service Advisory ===
    1414
    1515Once we have a date for the big move, we should announce it as a [wiki:email_announcement_lists service advisory].
    1616
    17 === All Members List ==
     17=== All Members List ===
    1818
    1919One month before our scheduled move, we should sent an email to [wiki:email_announcement_lists the all members list] announcing the project.
     
    3030 * We are able to access our Hurricane Electric IP range in both locations in August
    3131
    32 == Phase 0 ==
     32=== Phase 0 ===
    3333
    3434Phase 1 refers to the first two  weeks of the overlap period.
     
    3939 * Install new Riseup, MFPL and Tachanka servers
    4040
    41 == Phase 2 ==
     41=== Phase 1 ===
    4242
    43 Phase 2 will happen sometime around the middle of August.
     43Phase 1 will happen sometime around the middle of August.
    4444
    4545Pick a night and show up at 25 Broadway with a van at 2:00 AM. Take down all servers and transport them to 111 8th Avenue.