60 | | The first goal is to move all resources to MFPL so we can stop payment on the Canadian servers. The absolute deadline for this process is January 7 (based on the billing cycle). The goal is to move all servers by mid December. (Could this be done giving priority of attention in this order mx24, mx3, mx23, mx25 and mx1? that's considering financial matters of members). |
| 60 | The first goal is to move all resources to MFPL so we can stop payment on the Canadian servers. The absolute deadline for this process is January 7 (based on the billing cycle). The goal is to move all servers by mid December. |
| 61 | |
| 62 | ----Note:---- about the deadline for this process, we should consider different days for each server because the billing cycle is different for each one of them: |
| 63 | mx24 2011-12-04 mmsc - dedicated server |
| 64 | mx3 2011-12-09 laneta - mailman server |
| 65 | mx23 2011-12-25 rosalux - dedicated half server |
| 66 | mx1 2012-01-07 laneta - main server |
| 67 | mx25 2012-05-15 cimac - dedicated server |