3 | | * Term - I think we should think about this based on the term of the contract - in this case September 30, 2009. |
4 | | * Capacity - how many servers can we add between now and the end of the term? Rather than figure things based on how many servers we have now - I think it would be useful to try to predict server usage through the end of the term. We can figure expenses based on when the are installed - but I'm increasingly concerned about making sure we don't both expand servers at the same time. I think we'll need to estimate total capacity of the cabinet now and then see how many more servers can be added and then ensure that our plans through September won't exceed that. I would definitely expect MFPL to install at least one more server, probably two and at most three between now and the end of the term |
| 3 | * Term: September 30, 2009. That's the end of our contract with Bandcon - after which we will want to jointly negotiate a new contract with them. |
| 4 | * Cost: $860/month |
| 5 | |
| 6 | * Current Capacity |
| 7 | * Riseup |
| 8 | * Bufflehead |
| 9 | * New Server 1 |
| 10 | * New Server 2 |
| 11 | * MFPL |
| 12 | * axiom |
| 13 | * naomi |
| 14 | * ottorene |
| 15 | * pianeta |
| 16 | * pietri |
| 17 | * roy (turned off) |
| 18 | * chomsky (turned off) |
| 19 | * Shared |
| 20 | * paley (terminal server) |
| 21 | * Future growth - we seem to be at current electrical capacity. Our contract allows us to add a new 20 Amp circuit for an additional $360, something we may want to consider adding now. MFPL will need to add one or two more servers prior to September 30, 2009 and Riseup may also need to add new servers |
| 22 | |