v4 v5 6 6 * August 15: Draft of all postal mailings complete 7 7 * August 19: Mail merge process ready to go for postal mailing, copies made 8 * August 22: Nomination Period Begins 8 9 * August 22: Postal mailings goes out August 22, 2011 9 10 * September 1: Draft of Sept lowdown completed on Final Preparations 10 11 * September 5: September Lowdown Article released 11 * September 5: Phone calls begin 12 * September 12: Final Email to ''all'' member. 12 * September 5: Phone calls begin 13 * September 5: Draft of Reports Complete 14 * September 12: Final Email to ''all'' members. 15 * September 12: Voting System completed and tested 13 16 14 17 * Survey to members 15 * Draft of Reports complete16 * Nomination period begins17 * Voting system completed and tested18 18 19 19