| | 15 | |
| | 16 | == Timeline == |
| | 17 | |
| | 18 | Enrique is contracted to transfer mx23, that process has begun (virtual server has been allocated, process has begun) |
| | 19 | |
| | 20 | * November 15: new MFPL hardware is installed, 686-based virtual servers are installed for m24, mx3, and mx1 |
| | 21 | * November 22: rsync script for transfering all data from mx24 is completed and has run, testing begins |
| | 22 | * November 29: mx24 goes live on MFPL server, rsync script is prepared and run for mx3, testing begins |
| | 23 | * December 6: mx3 goes live on MFPL server |
| | 24 | * December 13: mx1 is upgraded from etch to squeeize, two weeks of support allocated for dealing with problems |
| | 25 | * December 20: rsync script for mx1 is prepared and run, testing begins |
| | 26 | * December 27: mx1 goes live on MFPL servers |
| | 27 | |