33 | | * January 10: mx1 is upgraded from etch to squeeze, two weeks of support allocated for dealing with problems |
34 | | * January 17: rsync script for mx1 is prepared and run, testing begins |
35 | | * January 24: mx1 goes live on MFPL servers |
| 33 | * January 10: mx1 is upgraded from etch to squeeze, two weeks of support allocated for dealing with problems: DONE |
| 34 | * February 9: [wiki:full-filesystem-rsync rsync script] for mx1 is prepared and run, testing begins |
| 35 | * February 12: pick date to execute transition |
| 36 | * February 12: lower time to live for all domain names hosted on mx1 |
| 37 | * February ?: Phase 1 transfer: all services except bind will be transferred |
| 38 | * Shutdown all services on mx1.iweb except bind (dns resolution). |
| 39 | * run final rsync of filesystem to mx1.mayfirst |
| 40 | * reboot mx1.mayfirst |
| 41 | * test to ensure sites are working |
| 42 | * change DNS entries to point to mx1.mayfirst (DNS is still running on mx1.iweb) |
| 43 | * All DNS changes are still made on iweb |
| 44 | * Ferbuary ?: Phase 2 transfer |
| 45 | * Rsync /etc/bind/ files from mx1.iweb to mx1.mayfirst |
| 46 | * Change authoritative DNS IP address for ns1.laneta.org to point to mx1.mayfirst |
| 47 | * Over the next three - five days, changes to DNS must be made on both mx1.mayfirst |
| 48 | and mx1.iweb |
| 49 | * Once the transition is complete, mx1.iweb can be retired |